Progress of rural road construction in Targwa village, Daik-U Township was inspected by officials from the Township Department of Rural Development on 22 October.
The officials inspected the current situation of the road construction and urged the responsible people to meet the set standard within the target date.
The project is being conducted with K 15 million funded by village development project and K 0.93 million contributed by public with technical aids of the department. The project is conducted starting from first week of September and now it has been completed by 75 percent.