THE Department of Rural Development under the Ministry of Cooperatives and Rural Devel­opment, Danu Self-Administered Zone, Shan State (South), conducted a field inspection on the morning of 1 June to observe the completion of a water pipeline installation project implemented in Htaminbaung Village, Kyaukpon Village-tract, Ywangan Township, to ensure year-round ac­cess to sufficient clean drinking water for rural residents.

 

The 3,800-foot-long water pipeline installa­tion project was implemented with Union-ap­proved funding of K22.31 million through co­operation between engineering staff from the Township Department of Rural Development and village residents. The project has now been completed in full.

 

Upon completion, 159 households with a population of 789 people in Htaminbaung Village will be able to access and use clean drinking water more easily throughout the year. — Cho Than Nyunt (Rural)