Construction of fire services station 75 % completed in Myothit Twsp

Myothit, 1 July
    

A four-storey apartment for employees from the Department of Fire Services is being built and the project is 75 percent completed so far.
    

Construction of the facility commenced in January this year and it is being built by a private construction company with K 421.2 million allotted by the local government in the current fiscal year. The building includes staff offices, apartments and ground floor for housing fire engines.
    

Magway Region MP U Than Swe, Township Administrator from the General Administration Department U Thein Zaw Oo and members of the township level quality inspection committee made a field trip to the construction site to look into progress of the building.